Video: Construction Change Order Fundamentals | Duration: 2852s | Summary: Construction Change Order Fundamentals | Chapters: Welcome and Introduction (8.18s), Speaker Introduction (75.735s), Session Overview (113.115s), Change Orders Overview (215.865s), Change Order Tracking (282.1s), Change Orders (349.205s), Change Order Importance (478.61s), Change Order Pricing (642.65s), Change Order Types (697.15s), Change Order Best Practices (970.505s), System Demonstration (1334.065s), Subcontractor Change Orders (2029.155s), Q&A and Polling (2300.255s), Change Order Types (2385.18s), Change Order Recording (2437.485s), Q&A Session (2519.435s), Training and Support (2618s), Q&A Session (2694.38s), Closing Remarks (2825.045s)
Transcript for "Construction Change Order Fundamentals": Good afternoon or good morning, depending on what time zone you're joining us from, and welcome to today's webinar. Couple quick housekeeping notes before we get started. We recommend Google Chrome for the best experience. The audio for today's presentation is streamed through your computer as there is no dial in, so please make sure your volume is turned up. You can download the slides via the resource tab in the top right hand corner of your screen. And please note that you will receive an email with a link to the on demand recording of today's session, which you can play back or share with anyone else who may find today's content relevant. As always, you can type in questions in the q and a box throughout the presentation. We'll get to as many of those as we can at the end of the session. And if we don't get to, online here today, we'll follow-up individually offline. So today's topic is construction change order fundamentals. This is part of our Construction Accounting University series, and, hopefully, you're gonna find some, good content in today's session. Quick introduction. I am John Ivers, vice president general manager here at Delta Computorees. I have over thirty five years of experience in the construction industry. Started my career in construction working for a large contractor. Various roles during my ten years there, and I've spent the last twenty five plus years serving the over 6,000 contractors that we have nationwide as the leader of the Deltek ComputerEase team. You know, my role is to make sure that we're equipping contractors the tools they need to manage profitability, drive growth, and meet the ever changing complex construction requirements. What we're gonna talk about today, the ins and outs of change orders and what they are, some of the common pitfalls, and how to avoid costly mistakes, the different types of change orders and when they are applicable, and best practices to streamline change order management, ensuring, you know, smoother project flow, faster payment, and better customer satisfaction. So before we get started, I'm gonna launch a quick polling question here. I'd like to know, who we have in the audience today. So I'd like to know what your current accounting or construction ERP system is. Maybe you're using Deltek Computorees. Maybe you're using Foundation, QuickBooks, Sage, Viewpoint, or other. And we'll leave that open for thirty or forty seconds. Give everybody a chance to answer that. I see it's kinda spread across a number of, Delta Computer East customers on the call today. So as always, we thank you and appreciate your business. A number of QuickBooks users on the call. I know certainly managing change orders can be problematic in a generic accounting solution such as QuickBooks. And then I certainly notice some, you know, a number from Sage, Viewpoint, and other solutions as well. So I think we got just about everybody's vote in, so I'll go ahead and share the results real quick. So as I said, kinda spread across the different, different solutions, but we'll go ahead and close that, and we'll go ahead and continue on. So... Alright. So let's talk about change orders. You know, what what are they... Let's let's start with an overview, and then we'll dig into into into some of the detail. You know, so a change order, at the end of the day, is an official document that reflects a change to a contract, a job that, you know, could include additions or reductions to the scope of work, a change in the pricing. A change could be an increase or a decrease, revisions to the parameters of the job such as the schedule. So you may have a change order that's requiring some additional work. And as a part... Not only you're gonna quote a price for that, but you're gonna you're gonna require an extension in the in the schedule to accommodate the additional work. And then certainly at the end of the day, there needs to be agreement from both parties. Both parties are gonna sign off on this. One of the things I think is very unique in construction when when we talk about change orders, when we talk to people outside of construction, they don't quite understand some of this, is that a lot of times, we we have to start the work before we actually get the signed document all the way through the system. So ideally, you know, maybe logically, maybe not ideally. Logically, maybe, you know, we make more sense. Okay. Once we get a signed change order, then we'll begin to work. But the... You know, in reality, because of the flow of the job, because of the the... When the work needs to be performed, we can't always do that. So a lot of times, we start doing the work off of a verbal authorization, maybe some written authorization, you know, before the actual signed document is provided us. So we need to make sure that we're tracking, and we'll see an example of that here in in in a little bit when we we look at a few examples in Computerease. You know, we need to make sure we're tracking the change orders from the time they are initiated all the way through until when they're approved and we and we can bill for them. You know, don't treat the change orders just as an after after the fact recording of the signed document. Why... I need to know that the change order has been initiated because in a lot of cases, I may begin or start to do the work, you know, some or all the work before I actually get the signed document all the way through the process. You know, when do change orders occur? You know, the the the customer, you know, sometimes is requesting a revision to the original scope. Maybe they're... You know, which is gonna cause an increase or reduction into the scope of work. Maybe I wanna add some additional work. I wanna I wanna change out the the type of fixtures that we're gonna use that was in the original contract. Maybe I'm... I need to... You know, we're we're gonna decide not to go forward with a certain portion of the contract. For whatever reason, you know, increase or decrease in the scope of work is gonna require a change. You know, a lot of times, maybe the initial job specs, you know, didn't reflect the reality of the project. No matter how it was drawn up, when we get out there in production and and go to and go to to build the the project, we find out we can't do it the the way it was originally drawn up, which is gonna require a change. Once again, could be an increase, could be a decrease. Maybe there's some unexpected conditions on the job site that warrant a change order. And, you know, there's gonna certainly be... You know, there could be some delays in the project schedule due to, you know, material or labor and or labor dependency. So change orders can occur for various reasons. And, you know, we're gonna talk about not only external change orders. So, you know, there's a a change order that requires a a contract change and a scope of work change. You know, there's also what I will call internal change order. So maybe I'm going to change something. It's not an actual contract change. It has nothing to do with the the owner or the general contractor, whoever I might be working for, whoever I have a contract with. But in a purposely built job cost accounting solution, we know there are reasons we we may wanna change something in the budget, change the way the budget was allocated. So a lot of times we can do that by internally issuing a change order. There's nothing to do with our contract, and... But I wanna move some of my budget from one line item to another for internal cost, you know, tracking purposes. Well, I don't wanna do that without an audit trail, and I can do an internal change to create that audit trail. We'll talk a little bit more about that here in a little bit. You know, why are change orders important? You know, that that... Certainly, we wanna make sure that we, you know, have a good working relationship with, you know, the... You know, whatever entity, the... Be it the owner or the contractor we're working for. You know, it's gonna make sure that both parties are agreeing to this work. There's not a dispute. You know, it it helps keep the process, you know, professional, you know, profitable, and transparent for for everyone. You know, we wanna make sure that the contractor and the customer and, you know, whether you're, you know, a sub or a general contractor, you know, the customer may be the owner, The customer may be the general contractor you're working for if you're a subcontractor or another subcontractor that you're working for if you're a subcontractor. But we wanna make sure that we, you know, we we have these changes documented, and it's gonna help us maintain that relationship. You know, change orders, you know, we're typically gonna have a direct impact on the cost, the time, and the contract amount. So what is it gonna cost? What are we gonna pay for it? And what is the time it's gonna take to do the work? So those... All those can be impacted by the change order. We wanna make sure that we're, you know, we're setting the right expectations and we're meeting those expectations. We know going into a job, they're going to be change orders. You know, we're we're... All... In all likelihood, depending on the size of job, it's... You know, it's be very rare that you would do a, you know, a a fairly good sized job without having change orders. And change orders are, once again, not designed to be more or less profitable for either side. They're, you know, they're not designed to penalize one side or the other. They're designed to make sure that we can get the job done in the best way and and the... That it needs to be done so we we can we can finish the project. And, you know, but if not managed properly, you know, change orders... I mean, you know, there... A lot of times there's a joke in construction that, you know, yeah. I didn't make any money on the contract. I made it all in the change orders. Well, that... That's that... You know, I think that's probably not typically the case. Change orders certainly are designed to be profitable just as the original contract was designed to be profitable. But there are also, you know, gonna be guardrails in place typically to make sure that you're not gouging your customer on the change order work. A lot of times, there's going to be limitations built into the contract when change orders occur as far as how how you can price the change orders, how much you can mark up the change orders. A lot of times, that's negotiated in the initial contract because the initial contract is going to have... Typically, it's gonna lay out the change order process. Make sure you understand the change order process before you go into a job. Before you sign the original contract, make sure you assume there are going to be change orders, and I need to know how that process works. Everything from how I'm gonna price out the change orders, what information am I gonna need to provide to support the change order amount. You know, when when you do the original bid, you know, I'm I'm bidding, you know, the the job on a, you know, the the fixed contract price, and I'm going to do all the work, the scope of work for that price. Well, you know, I don't... You know, a lot of times, the... Your customer doesn't have visibility into how you got to your to your bid. Now, you know, you did an estimate, you marked it up, and you got to the, you know, the ultimate sale price or the contract price. But change order is gonna be a little bit different. You know, you you may have to provide documentation on how you priced out that change order because we're gonna... Lots of... You know, it's gonna prevent the contractor from, you know, price gouging the customer on the change order work. So just make sure you understand the rules regarding change orders so you're not surprised when it comes time to initiate a change order. You know, there are different types of change orders. You know, a lot of time, you know, lump sum, which, you know, typically would, you know, probably be the most common, especially if you're doing a lump sum or a quoted contract amount. So, you know, the the project scope can be easily quantified and priced. You know, we're gonna establish, you know, the impact of the of the change and the and then the contract amount, and we're gonna, you know, detail the additional effort and what impact that has on the contract amount in the time line. Now, you know, typically, we're gonna see that. We're gonna have multiple change orders. You may have multiple requests for change orders that are combined into one change order. We'll see an example of that here in a moment as well. But... You know? Or you may have each individual request is signed off as an individual change order. But, you know, we wanna make sure we're tracking all these from the time we initiate them all the way through until they get approved, and, ultimately, we are able to bill for them and are paid for that work. Now if you're doing a job that is that is unit based, maybe you're doing DOT work, for for example, Department of Transportation and and, you know, whatever state you may be working in. Your your original contract is probably... You're getting paid a fixed price per unit, and the change order, you know, would be would be similar to that, would would work in the same way. So, you know, if there are identifiable units, we're gonna do that. You could... You know, you certainly could have a unit based change order that's attached to a lump sum contract as well. The... Maybe the change order work is gonna be broken down by the unit. But, typically, you know, I would see unit based change orders would would be applicable to a unit based contract that you have where you're getting paid a fixed price per unit of, you know, like, the... I'll use the DOT contractor, maybe a, you know, guard... Feet of guardrail that you're installing, you know, you know, road that you're... You know, pavement that you're laying, whatever that may be, you may be getting paid by the unit. So, you know, that that typically, you know, the... I see the unit change orders, you know, or typically apply where you're getting paid by the unit, certainly roadwork, you know, masonry might be a good example, landscaping a lot of times, flooring or some of the trades, where I I typically see unit based billing occurring and then corresponding unit based change orders. You know, you could have a zero cost change order. You know, once again, this is something what I... That more applies to those internal change orders. So there's no impact to the original contract amount. But I wanna I wanna keep track. I wanna keep an audit trail internally, for example, if I wanna move budget from one cost code to another. When we originally bid the job, it looked like... When we broke out our budget, it looked one way, but now I wanna move money from one cost code to another. Now I could just go in and, you know, deduct it from one and add it to another without creating an audit trail, But an internal change order allows us to to create that audit trail and keep track of that. So there's really... You know, there's no impact to the contractor or the overall budget in that example I just gave. But what I did is moved x amount from one cost category to another, and now I've created that audit trail. And then, certainly, we have time and material change order. So you may have a job that you're doing all the work as time and material. You know? But there also are situations where I may have a lump sum or fixed contract job, but we're gonna do the change order or at least a change order in some situations as time and material. So I... You know, I'm, you know, that that is not uncommon where you'd be doing a change order on time and material as part of a lump sum job. Certainly, you may have time and material jobs where where you're now doing additional work, and that that would, you know, would follow along with the with the time and material that you're already billing. You're gonna bill the the additional work as as well. But don't, you know, don't rule out the fact that you may have time and material or cost plus change orders even though you may have... The the original contract may have been lump sum. So, you know, lump sum contract could have lump sum change orders, or it could have time and material change orders or a combination of the two. And, typically, you know, the... Once again, time and material, you you know, you're gonna be... There's gonna be some guardrails in place as far as what you're charging for, you know, the the labor rates, what you're charging for material markup, what you're charging for profit. All that is likely, you know, predefined before you before you enter enter into the original contract. So what are some of the things we should be on the lookout for, and what are some best practices? And we're gonna take... In in a couple of minutes, I'm gonna I'm gonna use the Computerease system and give you kind of a couple examples of how, you know, kind of how some of these things work and kind of a... An overview for those of you that use Computerease already. Some of this will look familiar. For those of you that don't, I'm just gonna use Computerease because I think it's a good tool to illustrate, you know, how, you know, a good solid job cost accounting solution should be able to, you know, should be able to do those things for you and allow you to to track the change orders, have visibility into the change orders. You know, some of the things that we, you know, we see, you know, you could have, you know, the initial contract, you know, was was unclear. The scope was not clearly defined. That could potentially lead to, you know, change orders or an overabundance of change orders. You know, not having a change order process. I mean, in... Internally, you need to have... For every job you do, you should be treating change orders the same way. You should have a process in place to go through from the original tracking and initiation of the change orders all the way through to doing the work and, you know, completing the work and including billing for the work. You know, we're gonna... You know, we wanna make sure that we're introducing change orders when they're needed. You know, we wanna make sure that, you know, if the scope changes, you know, that a change order is typically gonna be required. So we're gonna make sure that we're doing that. And, you know, and we need to make sure that we're getting approval, you know, including signatures. And keep in mind, there could be various levels or various stages of approval. Maybe I've gotten a verbal approval. I I got a work authorization approval to begin the work even though I don't have the signed document. And we'll see an example here in a minute when we look at some some samples on how we should be tracking that, you know, in in our system so we can see what change orders are in what stage, and we can follow those through all the way through to completion. You know, change orders, at the end of the day, you know, they're they're, you know, they are changing the the scope of the initial contract. You know, they need to they need to be able to provide, the details that are easy to understand. The initial contract is going to almost always, if not always, spell out the change order process. So there's no surprises when it comes to change order time. You know, if you've done your due diligence when you signed the initial contract, you're gonna make sure that you understand what that process is. And a lot of times, you know, the the pricing and the markups have been prenegotiated as part of the orig... The original contract. So make sure you're aware of all that and you're prepared when change orders come, you know, come down the road. You know, as I said, it's always a best practice to, you know, walk through the contract with the customer and discuss the change order process before you sign the original contract. You know, in all likelihood, there's going to be change orders. So understand upfront how those are going to be managed and what the expectations are so you're not surprised. I mean, there... You know? And if you have a question on that, the time to address that is before you enter into the original contract, not when the change order... The first change order arises. You know, make sure that, you know, we, you know, we don't agree on doing additional work unless we have, you know, a change order. And maybe not a final approved change order, but we're gonna have a a a requested change order, and maybe we're gonna have that initial verbal authorization to begin the work in advance of getting the signed document. You know, you wanna make sure that we have a positive dialogue for the change order process, but there also has to be structure to that process. You know, no one no one should be, you know, rolled over on as part of the change order process. We don't wanna get bullied in in the change order process to where we're doing work that's not profitable. At the same time, the... You know, your customer's gonna make sure they're not, you know, bullied into into overpaying for changeover work. It should be, you know, should be a win win situation for both the... Your customer and you as the contractor. I mean, you know, no one's expecting us as contractors to do the work and have it not be profitable. It should be, you know, certainly profitable at similar percentage to what the original contract is profitable at. But, you know, make sure that you understand that process and and make sure you're, you know, you're having ongoing conversations with your customer about the change order process. You know, make sure that you understand the, you know, the... Either you... One, you should have an internal template that you use for, you know, request for change orders. But understand your customer may require a specific template. And once again, with the right system in place, you should be able to have that built into your system. So make sure you understand the, you know, the the format with which the change order request has to be presented. Make sure you have an internal process that's consistent across all jobs. So, you know, if I had to step in as a project manager on someone else's job, I... The change order process, I should already understand because it was the same as the jobs that I'm running. Make sure that we... You know, I don't want, you know, PM one to do change orders one way and PM two in our company to do change orders a completely different way. You know, certainly, you gotta do it the way the customer, the way the contract calls for, but make sure you have a, you know, a standard internal process, everything from tracking and initiating the change orders to make sure that there's consistency there. And I think, you know, it's important that you're looking for, you know, software tools that help you with this. And, like, once again, I'm gonna show a couple examples in the computery system here in just a few minutes. You know, as I mentioned before, you know, logically, you would think, you know, it would be better, as far as liability goes, if we just wait until we had the actual final signed document before we started doing any of the work. But we know that that's not the reality of the world we live in. So a lot of times, you know, we're doing this work based on a verbal or email or handshake agreement. But that's fine, but we need to make sure we're document that... Documenting that. You know, make sure that you're documenting everything along the way, every conversation, every email, and then certainly, ultimately, we gotta follow that through and get the signed document. Because, typically, that's what it's gonna take for us to be able to bill and get paid for that change order. But, you know, keep in mind, there are many forms of documents. There are, you know, contracts. You know, an email can be seen as a contract, a, you know, a conversation. So, you know, if you've if you've got verbal approval to proceed, you know, that can be that can be taken as a contract. So we'll make sure that we we have that, we have that information, we have that documented. So I'm gonna go ahead and I wanna show a couple examples here in Computerease of how we're tracking change orders. So give me just a minute here to bring up my Computerease solution. As I as I mentioned, for those of you that are using Computerease today, this probably looks, certainly looks familiar. But for those of you that are not, you know, this is just an example of how we're managing things in a purposely built job cost accounting solution such as Computerease. So I'm gonna go in and I'm gonna go in and start with the... My job dashboard. The job dashboard is a place I can go to see everything about a particular job. So I'm gonna start here. When I look at the job dashboard, we're gonna see things like, you know, our original contract, our approved change orders today. We'll get into the detail of this here in a minute. So these are the change orders that have actually been approved. We'll look at a detailed list of that in a minute. And then the current contract and the, you know, and the current estimate and the current the current cost. You know, if I wanna see a detailed breakdown of the change orders, I can see a list of all the change orders. There's the list of all the change orders that have been approved, the contract, the the budget amount. Here's the... Our request number. Here's the change order number. Notice that in this case, you know, two of our requests, number 2 and 3, were combined into change order number 7. So, you know, it's important that we're tracking both our our request number and the ultimate change order number. But notice I also have pending change orders listed down here. I have change orders that have been that have been rejected or denied. So we're tracking that. You know, when it's approved, it's gonna show up as a... As an addition to the contract, in addition to the budget, but I need to be able to track that along the way. Now we can also... You know, I think if you have a good system like Computerease, you certainly have the ability to include a change order even though it's not officially signed off on. You can have it included in the contract amount and the budget amount, whereas, another change order that's still being reviewed could not be. So you should have some flexibility to do that. You know, we're able to look at we're able to look at things. We're able to look at the at the contract. We're able to see customer change orders, original budget, change orders, revised budget. We're able to see changes, like, you know, here where we have an internal change order, where we moved something from one item to another, and I'm able to see that reflected in, you know, in in my, you know, in my job cost report. So those those are some of the things that we wanna be able to track. I wanna be able to look at all the change orders. I wanna see them, you know, the the detail of each and every change order. I wanna see, you know, in the status. I wanna see those that have been approved, those that are still pending, those that have been denied. I wanna be able to go... If I wanna look at more in a in a log type view, let's go over and look at the change orders here in a in a list view. So here's a list of all the change orders on this particular job. So I can see all the change orders. Maybe I wanna sort by status. I wanna sort by our request number. I wanna sort by their change order number. What... You know, you have the ability to sort this and look at this in many different ways. I wanna be able to drill down and see the detail of this particular change order. So here's the change order, and I wanna see the events, when we initiated, when they gave us a verbal, when they gave us the final signed document. Notice that, you know, change orders could have predefined, you know, markups on here. I've got I've got markups by overhead and profit. A lot of times, that is driven from the initial job creation, whereas part of the original contract, we have defined that change orders, you know, are gonna be marked up at a particular rate. So if I wanna go and look at the the markup table for this particular rate, I can see, okay. Well, what are the what are the markups rates for those change orders? So we can have that already predefined. So when I initiate a change order, we're gonna we're gonna see that. You know, I'm looking at change orders here on one job. I could certainly... You know, I could run the report or I could look at change orders across multiple jobs or maybe I wanna see just all the pending change orders on this job. So I'm going out to a going out to a job meeting, and I wanna see... I wanna get an update on all the all the pending change orders. When I initiate a new change order request, once again, I'm gonna do it right from my job dashboard here. I'm gonna come in. I'm gonna enter a new change order request. You know, this is the next request here. You know, request number 38 for us here on this particular job. You know, I'm gonna go ahead. I'm gonna create a... An itemized breakdown of what this change order entails. So, you know, I'm gonna create a request. You know, we're gonna add some additional work. You know, I wanna go ahead. I'm hoping to get a response by the end of next week. You know, this is a customer change order, you know, so I'm gonna I'm gonna rate this. If I don't think we're gonna get it or I think it's just a possibility or I'm confident that we are going to get it, we're gonna use those predetermined rates. And I'm gonna go ahead and say we're initiating that today. So John is initiating that today, and I now have a new pending change order out there. Now I'm gonna go ahead because I told her I'm gonna give the detailed breakdown. I'm gonna say, okay. We've got the, you know, additional labor on this particular job. We had a... An agreed upon rate for the labor in the in the contract. So, you know, what cost code is it gonna go to? I can put it to its own separate cost category, or I can put it to an existing cost code. So if I wanted to go, you know, add another cost category for this particular job to put that change order. If I can track the change order in a... In its own cost code, I think that's always recommended. Sometimes that's not practical. But in this case, you know, I wanna go ahead and I know that I can separate out this work, so I'm gonna go ahead and build a cost category. Not putting any budget in there. It's gonna... That's gonna come from the change order. But now I'm gonna go ahead and I'm gonna put that change order there in our new cost category and say, okay. We got we got labor, and then we also... Maybe we're gonna have some material. And I could have, you know, a list of prebuilt items that I'm gonna put on the change order. You know, I got a 100 feet of pipe. Once again, going to that same cost code for the change order. But now I've taken this change order. I've I've priced it out here, and I'm gonna go ahead and submit the request for change to our customer. But I've got labor material. I've got that overhead and profit, that 1510% overhead and profit that we said we were gonna get. And I can put any detailed notes here that I wanna include. We can have additional fields of information. Maybe this is gonna increase the contract by five days to do this additional work. I wanna go ahead and include that. I could attach any documents to go along with this, but then I've got a change order, the request form that I'm gonna send, and once again, I could have different formats. So you may have a standard format that you're gonna use. You may be using the format that they require, but, you know, in this example, you know, here's the here's the request for change, you know, prepared and ready to send over to our customer for approval. So we've got the change order. We've got it in the system, and we now have a pending change order that we're tracking. You know, there's our change order request form that we just generated and that I'm gonna go ahead and send over and get get signed off on. But now if I look... If I come back over here to the change order tab, you know, I got a new pending change order that's now showing on the list. So when I go to the change order breakdown, you know, I can see the pending change that we have now initiated. You know, $850 we're asking for in the contract, and and our budget's gonna go up by $680. Now I can track that through, you know, through the through the system and through the process. So, you know, I have the change order. You know, later on, as we get further on in the in the process, I'm gonna come in, and I'm gonna go ahead and and add, you know, add the next stage in the in the sequence so we got a new event. So they gave us a verbal. You know, they gave us a verbal. We we don't have it, don't have it finalized yet, but I do have a verbal, but I... And I... Which I now am am creating that audit trail. And then ultimately, you know, hopefully, we get the final approval, get the signed document back, next week. But now I've got that... I've created that audit trail on that history for that change order. And once that change order is approved, then you'll notice that the contract is going to be increased because now that... Now it'll be part of our contract and budget because we have the approved change order. So, you know, we're looking at, you know, just one particular job, but I wanna be able to look at all change orders across all jobs as an example. Maybe I wanna come in here and I wanna run my change order report. I wanna see all the change order reports, and I wanna... But I wanna see just the pending, and maybe I just wanna see a summary, you know, by job, and there's a list of all the pending change orders, job by job. I could run that same report in detail. I could drill down and see the detail. But remember, we're tracking these from the time we initiate the work, and then they carry forward to the billing. So when I go do... And, you know, that that first example we gave, that was a lump sum job, so I'm gonna go ahead and get ready to do the next billing. Well, you know, the the system should know that when you go to enter work complete that you have change orders that have not been previously billed. So when I go to go ahead and generate the invoice, you know, I got change orders that haven't been billed for yet. I'm gonna go ahead and add those to my schedule of values. I wanna go ahead and add those as a separate line item or include those as part of an initial... As part of an already existing line item. So there should be coordination communication between the job costing system and your change order system. So, you know, change orders should be, you know, should be very easy to track. You should have... You know, when when I'm looking at... Once again, I'm looking at that change order report or I'm looking at the, you know, the job dashboard as I go from job to job, I wanna be able to see the change orders. You know, each job's gonna show me the, you know, the approved change orders, the pending change orders, but I wanna be able to see all that information. I wanna be able to run those reports and look at all the all the change orders, both approved, pending, denied, as well as looking at the profitability of those change orders, especially when we're able to break that out and put it in, you know, in their own cost category. So just... I wanted to to spend a few minutes in Computery. So The the other thing that I I do wanna... I actually am gonna mention real quick. It's really important that we're also tracking change orders for our subcontractors. So if we are... Depending, you know, whether we're a sub who has subs or a general who is is using subcontractors, I wanna be able to track all of the change orders for my subcontractors. So when I'm looking at my subcontractors and I'm looking at the, you know, list of all the subcontract reports, I wanna look at I wanna look at the change orders. I wanna be able to create a change order for my sub. I wanna be able to tie their change order to my change order, you know, if that's the case. I mean, that's not always the case, but in a lot of cases, certainly, I'm gonna track I'm gonna track my change order. Their change order is gonna be part of of my overall change order. So we wanna make sure that we're looking at all that. We're looking at those we're looking at those reports. We're we're able to track and manage the manage the change order. So if I wanna look at the, you know, my subcontract dashboard, I wanna look at all my subcontractors, you know, I can see that. I can see the change orders. I can see this by individual job. You know, if I wanna go look at all the change... All of my subcontracts for a particular job, I'm gonna see the detail and I'm gonna see the change orders, you know, for each of my each of my contractors that on... So I'm gonna see the original contract, change orders, current contract. So when you're initiating a change, you wanna make sure that you're including that as part of as part of your change order. So if I go back to I go back to my job real quick here and if we were to do another another change order, you know, it's important that I'm... I include the sub... The subs change order as well. So I'm gonna go ahead and create a new detailed change order, and maybe in this case, it's all all subcontract work. We'll make it make it pretty simple here. You know? So I gotta add some sub work here on this particular job, and I'm gonna I'm gonna do it as a change order to to them. So same same information. You know? We're gonna initiate the change order. But now when I add when I add the item here, I'm gonna go ahead and add either a new subcontract or a change to an existing contract. So here's the existing contracts that I already have on this job, and maybe I'm adding a change order to this particular subs contract. So now I'm creating the subs change order. So this is gonna be pending because I'm not gonna approve theirs until till ours is approved. You know, it's gonna be... If it's part of my change order number, I can assign it their change order number. I'm gonna go ahead and put in the, you know, the... Once again, the the scope of work and the audit trail for for that change for for our subcontractor. So, you know, we can manage that throughout the throughout the process and be able to be able to track that through and get those... And get the change order for our subcontractor approved as well. So, you know, I've got the I've got the change, creating that, and now I'm gonna go ahead and put in, you know, put in the dollar amount. So we're gonna go ahead and... And I can put in the scope of work, and, you know, we're gonna put in the individual items. So what is the item? You know, once again, what cost code is it going to, and what is the... You know, they're gonna they're charging me a lump sum of $5,000. You know, I can put in, you know, the the scope of work, generate the the change order, you know, for the sub, and now I've got their change order tied to my change order. So, you know, $5,000, I'm adding my overhead and profit, and I've now got a pending change order request for that $62.50. So if I, you know, if I go down and look at all of my change orders, I'm gonna see the I'm gonna see the change order, and I'm gonna see that most recent pending change order, and there's the pending change order that is tied to my subs change order. So make sure we have that relationship. I mean, that subs change order, in most cases, you know, not not necessarily all cases, but in in most cases, it's likely tied to a change request that you're making. So make sure you create that link between the two so when you get your change approved, you can approve your subs change, and you have that audit trail. So that's just a couple examples of how, you know, powerful the computer system can be in helping you manage change orders. So I'm gonna go ahead and close out of here. I'm gonna come back, and we'll open it up to some questions here. I know I got some presubmitted questions. I got some others that have come in. But, let me go ahead and go back to the slide deck here for a minute. Sasha, I'm gonna go ahead and launch one last polling question here before we jump into q and a. So if you'd like to be contacted to learn more about Deltek Computers in general and specifically maybe on how change orders can can, change order tracking and process can help, your company, please check the yes box there. So let me go ahead and open up the polling question here. So I'll go ahead and open that up. So if you'd like to learn more, just go ahead and check yes in the in the polling question. I'll leave that open for about thirty seconds or so. And while we're doing that, I'll go ahead and get some questions queued up here. So I got a lot of questions that have come in. So let me go ahead and get to as many of those as we can. So, just a couple more seconds here, and I'll go ahead and close that poll. Give that about another ten seconds or so, but I'll go ahead and take a couple questions while we're waiting for that. Can I run a report in Computerease that shows all the change orders and the status of the change order? Sure. Yeah. So that... You know, I ran... You can run that report, you know, and I I showed an example of that in Computerease. I can ask it for a list of all the change orders by job. I can ask it just for a particular status or all statuses. So, yeah, you have the the ability to run those change order reports and slice and dice that a number of different ways. What is the difference between an item... Itemized and a nonitemized change order? So nonitemized would be I'm just gonna give the lump sum amount. I'm not gonna break it down into individual, you know, labor items, material items. You know, I I may, in the itemized, I may have journeyman labor, apprentice labor, you know, material type a, b, and c, where in a nonitemized, I'm just gonna give the lump sum budget for the change order. I'm gonna go ahead and close that polling question now, and I'm gonna just put up some general contact info as we dig into some more of these questions here. So I'll put some general contact info on the screen. And and as a reminder, if you missed any of the sessions in our Construction Accounting University, when you get the link for today's session, feel free to go there and check out the, you know, the on demand events, or you can certainly go to deltek.com/cau. Alright. Looking at the questions here. So I covered that one. Do you find that change orders are best recorded in computers up within the original budget lines, or I've seen some companies enter change orders as their own budget lines down below? So I don't think there's a right or wrong answer to this. Well, what I would say is if you can separate the cost, you know, clearly and accurately, I think it's... I I think it's always preferred to have it as a separate budget line item, but sometimes that's not practical. I can't differentiate between the original contract work and the change order work. I just know that we're, you know, we're... We we gotta run some extra pipe or we gotta do, you know, something extra that you may not be able to separate. So, you know, the the the question I always have is is, okay, how are we gonna track the cost, and can we easily separate the change order cost from the original cost? Sometimes that's not practical, and it makes more sense to put it into an original... Add it to an original bud... You know, budget line item. You'll still see the original budget, the amount that was added for the change order, and the current budget, but you, you know, you won't see it broken out as a separate line item. But if you can break it out as a separate line item, I always think that's the preferred method. Alright. Looking at the questions here. Sorry. A couple more duplicates here. We're interested in learning more. Can you please contact us? Yes. So anybody that that asked that question... I got a couple other questions here I see from couple people that are on QuickBooks that are interested in learning more about Computery. So if you either answered yes to that polling question or you have... You're asking a question in the q and a about being contacted, we will certainly reach out and and talk more. You know, where is the data sitting in the Deltek cloud environment? Yeah. So we, you know, we have our secure cloud environment, which is where, you know, which is where your computer each data will be, you know, will be hosted. But we'll we'll be happy to to reach out and and walk you through and talk you through that. How long will the on demand events be available? Yes. They are avail... I don't know the exact time frame, but I will certainly follow-up and answer that question. I... I'd... I apologize. I don't know the answer off the top of my head, but we will certainly, find out. But I know they are available for some... For quite a period of time. Let's see. Are the material prices, labor rates loaded into this changeover tool per geolocation? Like... Well, they... You you can build a library. So, yes, you know that one... A job in one geo may have different rates than a job in another geo. So you have unlimited libraries of change order pricing you can build into computer resystem. But great question. If you have multiple POs on the same job, can you enter them as change orders? Not sure I'm following that. I I I... Yes. I... I'm assuming you're saying you have a job, and they've issued you multiple purchase orders to do the work, and you wanna treat them as change orders under one job. But I... I'm a little unclear of of exactly what you're asking there, but we'll certainly have someone follow-up and and, have a conversation. Be happy to answer that for you. We'd like to get some training regarding the markup, percentage. So, yeah, that... Certainly, we could, you know, we can have someone reach out and do and do one on one training for you, but also know if you're you're an existing Computease client, we do have meet the expert sessions every Tuesday, Wednesday, and Thursday hosted by one of our senior consultants, or you can just pop in and ask any question. And that would be a that would be a great question. You could pop in and ask, and they could do a a quick session, you know, right there in the meet the expert sessions. But... You know? So we'll reach out and make sure you have a link to how to register for those meet the expert sessions or... And we'll also have someone reach out in in in case you wanna get some individual training. So great great question. Is there any limit to the number of change orders we can track on a job? Yeah. Great question. No. No limit no limit whatsoever. We're interested in possibly moving from QuickBooks to Computorees. Can you tell us, how long that transition typically takes? Great question. Typically, you know, six to eight weeks. You know, could be shorter. It could be a little bit longer, but as a general rule, if you figure, you know, around a six six week turnaround. But it it depends on the size of the company and some of the things. We'll reach out and and talk through that in a little more detail with you. So it's a great question. Another one here. You know, we're interested in getting some pricing information on ComputeRease. Can you please provide that? Once again, couple questions we need to ask, you know, number of users, what configuration you're gonna need. So we will certainly reach out and be able to to answer that for you and and come up with a, you know, come up with a price, you know, a price quote for you as well as discuss the the timeline of of implementing, computers. Just looking here if there's any other questions. Yeah. Can I get the link for the meet the expert sessions? Yeah. We'll certainly provide that link to everybody after today's session. Can I upload from Excel or CVS? Yeah. So we do have the ability to import a change order information. So... Yes. Any idea about the fee to use computers per year? Is that based on per user or contract dollar value? Yeah. It's not not at all related to the contract dollar value. It is based on the number of users number and the configuration. So we'll reach out and and be happy to to share that with you once we know a little bit more about your your company's configuration. So great questions. So I think I've covered most of what has come in. Yeah. I got another question around imports into ComputeReach. So, yeah, there are imports. Do we have various import capabilities into ComputeReach? And we can reach out and kinda walk you through, you know, what the import capabilities... What import capabilities exist for Computerease. Alright. So with that, I think we've covered most of the questions. Like like I said, you will be getting a link to the on demand recording. Please check that out, and feel free to check out all of our wonderful content in our Construction Accounting University by visiting deltech.com/cau. So thank you all for your attendance today. We'll be reaching out to, a number of you very shortly, but, appreciate your time. Everybody have a good day, and we'll see you on the next webinar.